No content available.
- Personnel
- Safety
- What is in the Box
- Tools and Equipment
- Materials
- Preparations
- Installation Overview
- Charger Wall Mounting Bracket Installation
- Charger Mounting
- Electrical Panel Power Cable Connection
- Charger Assembly
Personnel
One certified electrician
Safety
WARNING
Before installing the charging station, refer to safety instructions.
WARNING
Risk of Electrocution
There is a risk of electric shock. Do not alter, relocate, drill, or remove any component without consulting with an EV Meter certified team.
WARNING
Local Electrical Regulations
All installation actions must be done by a certified electrician and according to the local regulations.
WARNING
Safe Use of the Charger
Do not use the charger if it is cracked, corroded, frayed, broken, or the LED indicates internal error.
What is in the Box
- Quick Guide
- Warranty
- 10 × M4 Hex screws
- 2 × Phillips screws
- Charging station
- Front frame
- Bracket
Tools and Equipment
- PZ2 or PH2 screwdriver
- Flat 4mm screwdriver
- Hex H3 screwdriver
- Level
- Drill
- Hammer
- Voltmeter
Materials
- 4× Size M6 stainless steel screws
- Two flexible N2XY 5X6 mm² Cables
- Dowels
- Charging Station Kit
Preparations
NOTE
Kit Unboxing
The kit unboxing is to be performed only by a certified electrician followed by a visual check for any damaged/ broken parts. In case of any damage, contact EV Meter support.
- Unbox the charging station kit.
- Make sure two MCBs and two RCCBs are installed in the electrical panel, according to the following table:
Connection type | Max Power output | Circuit breaker | RCCB |
|---|---|---|---|
3 Phase | 22 kW | 3×32 A | 4P - 40A - 30mA RCCB Type A |
1 Phase | 7.36 kW | 1×32 A | 2P - 40A - 30mA RCCB Type A |
- Turn off the charger power using the circuit breakers.
- Using a voltmeter or any equivalent device, make sure that all the power to the charger is turned off.
- Using flexible N2XY 5X6 mm² cables, route the power cables from the circuit braker to the charging station. Make sure the cables are long enough to reach the charging station.
NOTE
To provide quick power off, in case of emergency or maintenance, install an emergency switch, according to the local regulations and the power input to the charging station.
EV Meter recommend installing an emergency switch specifically for the charging station, next to the charging station.
Installation Overview
CAUTION
Installation Conditions
The installation must be performed in dry conditions.
The installation process includes the following steps:
- Charger Wall Mounting Bracket Installation
- Charger Mounting
- Electrical panel Power Cable Connection.
- Charger Assembly
Charger Wall Mounting Bracket Installation
- Open the front cover of the charger.
- Disconnect the harness connected between the charger and the front cover.
- Remove the front cover from the charger.
- Remove the wall mounting bracket from the back of the charger.
- Place the wall mounting bracket on the wall.
- Using a drill, drill four holes, according to the holes placement in the charger’s wall mounting bracket.
- Using a hammer, hammer four dowels into the holes.
- Using a screwdriver, screw four M6 screws, to secure the wall mounting bracket.
- The wall mounting bracket is attached to the wall.
Charger Mounting
- Align the sockets on the charger with the anchors on the charger wall mounting bracket.
- Place the charger on the wall mounting bracket.
- Using a Phillips screwdriver, install two Phillips screws on the bottom of the charger, to secure the charger to the charger wall mounting bracket.
Electrical Panel Power Cable Connection
WARNING
Risk of Fire
There is a risk of fire. Do not alter, relocate, drill, or remove any component without consulting with an EV Meter certified team.
CAUTION
Cable Placement
Make sure the cable is not placed in the way of any pedestrians, vehicles, or objects.
- Loosen the two cable glands on the bottom of the charger.
- Insert the 5X6 mm² cables trough the cable glands.
- Connect the L1, L2, L3 and neutral cables to the charger meters according to the following diagram and the meters indications
- Connect the ground cables to the terminal blocks.
- Tighten the two cable glands on the bottom of the charger.
Charger Assembly
- Connect the charger cover’s harness to the charger harness according to the following figure.
- Place the charger cover on the charger.
- make sure the charger cover is fitted in the charger’s socket.
- Using an Allen bit screw 10 M4×10 Allen screws to secure the charger cover to the charger.
- By hand force, install the front frame.
Comments